The next phases of the Centennial fiber network build
Christine Ottoni • May 16, 2018
if( has_post_thumbnail( $post_id ) ): ?>
In our Centennial progress reports, we offer as much information as we possibly can on the fiber network build process. We’ll also talk about Ting events, promotions and some of the work we’re doing in the Centennial community. Check back regularly to keep up to date on the latest.
Construction continues in Phase 1A and Phase 1B
As we covered in our last construction update, we’re on track in Willow Creek 1 and 2 and anticipate lighting up our first fiber customers this summer.
The deadline to pre-order (and secure $250 off your startup costs on Ting gigabit) in Willow Creek 2 is June 30, 2018.
We’ve also been working simultaneously in Phase 1B, starting with Walnut Hills, with plans to begin fiber construction in Hunters Hill this summer.
The deadline to pre-order for Phase 1B Walnut Hills is July 31, 2018. We’ll be announcing the pre-order deadline for Hunters Hill in the near future.
Up next: Phase 1C
We’re excited to announce Phase 1C coming soon to the Centennial fiber build.
Phase 1C Willow Creek 3 and Willow West
Next month, our teams will start construction on Phase 1C in Willow Creek 3 and Willow West.
If you live in these areas, expect advance notice from us by mail (and email if you’ve pre-ordered) before construction begins. For now, take a look at our post on what to expect from construction when we come to your neighborhood.
The pre-order deadline for Phase 1C is October 31, 2018.
Make sure to get your pre-order in to secure the best discount available on Ting gigabit Internet!
Pre-order Ting and save $250
Pre-order Ting gigabit Internet for $9 and get a $250 discount on your startup costs. That completely covers installation in most cases, with $50 leftover to put towards the purchase of your router or your first Ting bill. You also get installed as soon as we’re able to connect your address to the network.
Remember, the deadline to pre-order for Phase 1A, Willow Creek 2, is June 30, 2018.
The deadline to pre-order for Phase 1B, Walnut Hills, is July 31, 2018.
The deadline to pre-order for Phase 1C Willow Creek 3 and Willow West is October 31, 2018.
If you aren’t in these phases you can still pre-order Ting!
Pre-orderWe had a party for Willow Creek 1 and 2

It was a day of food trucks, touch-a-truck and balloons. We had a great time celebrating crazy fast fiber Internet with the Willow Creek 1 community. It was awesome meeting everyone and answering all of your questions. We also gave away an Amazon Echo. Thanks to everyone who braved the weather and came out to see us.
We’ll be throwing a party for Phase 1B very soon. We’ll send your invitation by mail and email if you’ve pre-ordered.
State of our City Luncheon
In April, Ting Internet was a presenting sponsor of the 14th annual State of Our City Luncheon. We were happy to see that fiber was the first objective on the city’s 2018 list.

Make sure to follow us
Stay up to date with everything Ting is doing here in Centennial. Follow us on Ting Centennial Instagram, Facebook and Twitter for updates and fun contests as well.